  SHANNON AIRPORT (EINN) PAVEMENT RECONSTRUCTION WORKS ON TAXIWAY H1 AND H2

Commencing in June 2026, for a period of approximately 1 month, reconstruction works will be carried out to damaged pavement on Taxiways H1 and H2. The work areas are depicted in Appendix 1.

Taxiway H1: Reconstruction works in this area will be carried out between 08:00 and 15:00 (UTC), Monday - Friday.

Taxiway H2: Reconstruction works in this area will be carried out between 16:30 and 04:30 (UTC), Monday - Friday, to minimise the impact on aircraft operations.

Operational Implications:

  1. Specific operational restrictions, if necessary, will be promulgated by Shannon Airport Airfield Notice (SAAN) and /or NOTAM as required, with reference to this Supplement.
  2. If low visibility conditions occur, or are forecast to occur during planned working hours, reconstruction works will not be carried out.

Exact dates and times of the works will be promulgated by NOTAM with reference to this Supplement.

Note, time and durations may vary during the course of the works and within work areas.